Filtering by Activity Codes in P3e

Emmanuel UdoMember for 22 years 8 months
Created
3
2
0
Ladies & Gentlement,
I need to filter by Activity Codes. The schedule was prepared using User Defined Codes. However, in attempting to filter by Activity Codes (eg. by Area, Location etc) only activities appear.
Can any body out there advise on what to do?
Regards.

Emmanuel

3 replies

Oldest first
  1. 0
    Emmanuel Udo ·
    Mario,
    When i run thet filter I expect the filter dialogue box to display the code values/ descriptions for me to select from.
  2. 0
    David Kelly ·
    Emmanuel

    It is NOT possible to make a filter ask you for the value. When you run a filter in P3e it must have the value(s) you are looking for specifically coded in the filter - so for example a filter to select activities by the phase of a job cannot ask you "which phase" when you run the filter, you will require to create one filter per phase.

    The primvera product SureTrak has this capability, and is very usefull.
  3. 0
    Christian Adrian De Vera ·
    Emmanuel

    David is right, you need to create activity codes and values first coz the one that you have right now is only a code in the user defined field, thus when filtering only the activity descriptions apear and no band grouping your activities...

    Cheers!

    Christian