export activity codes

Marcio SampaioMember for 20 years 11 months
Created
2
1
0
Is it possible in the P3e to export activity codes of a project to another one in distinct data base? I made a test exporting the XER but it only exports the codes that had been used, codes that were created but it were not used, it did not export.

Regards.

2 replies

Oldest first
  1. 0
    Niek Zonneveld ·
    That’s correct, it only exports codes which you use. Which is neat because you don’t want to drag stuff along that you don’t need. (i.m.h.o)

    Select all codes you want to export by attaching them to one (dummy) activity, and you are done.

    Hope this helps,

    Niek.
  2. 0
    Marcio Sampaio ·
    Thanks a lot Niek!!