UDF - Loosing data!!!
In the Open Standard
Amir DadbakhshMember for 22 years
- Created
- 5
- 3
0
Dear Planners
I define some activity codes for my time schedule (in primavera 5.0). When I copy mentioned project (I select copy activity code too in dialog box) just some value of activity codes be copied and most of the value are lost. I don’t know how it might be happened, is it primavera bug or not?! For example:
Original project:
Activity no.1 (activity code value)=M
Activity no.2 (activity code value)=M
Activity no.3 (activity code value)=M
After copying mentioned project
Activity no.1 (activity code value)=(blank)
Activity no.2 (activity code value)=M
Activity no.3 (activity code value)= (blank)
Finally I solved this problem by using global change (whenever I copy a project I have to run global change to fill activity codes!!!!!)
I’ll be really glad if anyone of you have the same experience and you could solve that problem, put your solution here for using by me and other fellows.
Kind Regards
Amir Dadbakhsh
I define some activity codes for my time schedule (in primavera 5.0). When I copy mentioned project (I select copy activity code too in dialog box) just some value of activity codes be copied and most of the value are lost. I don’t know how it might be happened, is it primavera bug or not?! For example:
Original project:
Activity no.1 (activity code value)=M
Activity no.2 (activity code value)=M
Activity no.3 (activity code value)=M
After copying mentioned project
Activity no.1 (activity code value)=(blank)
Activity no.2 (activity code value)=M
Activity no.3 (activity code value)= (blank)
Finally I solved this problem by using global change (whenever I copy a project I have to run global change to fill activity codes!!!!!)
I’ll be really glad if anyone of you have the same experience and you could solve that problem, put your solution here for using by me and other fellows.
Kind Regards
Amir Dadbakhsh
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?