Skip to content

Creating a graphic reports in P3 v5

Andrew PodolnyMember for 21 years 11 months
Created
3
1
0
Hi there.

Does anybody know how to make Graphic report in P3 v5.
I need the Graphic report for cost distribution S curve.

Thanks a lot in advance

Andrew

3 replies

Oldest first
  1. 0
    Paul Harris ·
    Andrew

    www.DecisionEdge.com

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Peter Lloyd ·
    Hi

    Not 100% sure what you want to do here but check out the activity usage profile and plot the EAC curve. This will give you a cost S-Curve which can be compared with the budget.

    This S-curve will take into account the WBS settings for the WBS element the activities are in but if the EV settings are left as ETC = remaining cost for activity and the EV technique set as Activity percent complete then you will get an s-curve based on the activity percent complete with no no adjustment for CPI on the forecast


    Peter


  3. 0
    Marcio Sampaio ·
    Activity usage profile or Assignements (in this option u have to copy and paste to excel)

    Also look for ather threads about S-Curve.

    Regards.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?