Hello,

I have uncertainty about when Export a project from Primavera 5 to P3 format. When I open this file in P3,it lose the baseline created in P5?

Thanks,
Mauricio

1 reply

Oldest first
  1. 0
    Karim Mounir ·
    try this:
    restore the baseline which u are using in P5 first then export it to P3.
    after this export the updated schedule separately.