Exproting P3e expenses to P3
In the Open Standard
Rami Al HaddadMember for 21 years 4 months
- Created
- 2
- 1
0
Hi All,
Here is the issue... plain and simple ;)
> I’m using P3e... my client uses P3...
> I did all the scheduling in P3e... and then exported the project to P3
> Quiet Honestly... I knew that activity expenses will not export (those that are not loaded on resources) ;)... client finds out... yep you figured! He wants his expenses!!!
I heared once that there is a like work-around this issue that would get those expenses from P3e to P3... btw... I’m still using P3e/c v4.5 (company still making a decision on upgrading ;) )
can anyone help...
Here is the issue... plain and simple ;)
> I’m using P3e... my client uses P3...
> I did all the scheduling in P3e... and then exported the project to P3
> Quiet Honestly... I knew that activity expenses will not export (those that are not loaded on resources) ;)... client finds out... yep you figured! He wants his expenses!!!
I heared once that there is a like work-around this issue that would get those expenses from P3e to P3... btw... I’m still using P3e/c v4.5 (company still making a decision on upgrading ;) )
can anyone help...
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?