Displaying all activity codes used in a project
In the Open Standard
Bijaya BajracharyaMember for 21 years 7 months
- Created
- 5
- 3
0
In my P3ec database, there are hundreds of global activity codes. Some activities are assigned some of those codes. Is there any way to know which codes are used in a project?
When you try to assign codes to an activity, there is always a filter for displaying only current project’s values. But when you add column for activity code, the only choice that is available are group and sort by Categorv or List. Both choice lists all the codes. I want to see only those codes which are used in the current project.
Does anybody know how to do it?
When you try to assign codes to an activity, there is always a filter for displaying only current project’s values. But when you add column for activity code, the only choice that is available are group and sort by Categorv or List. Both choice lists all the codes. I want to see only those codes which are used in the current project.
Does anybody know how to do it?
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?