Actual, Budgeted, Remaining Early & Late units

Karim MounirMember for 20 years 6 months
Created
3
2
0
Hi,

I made a revised target schedule and i want to clarify some info here regarding the resource distribution (used in Tracking layout in p5):

1- The Actual units shall remain the same.
2- The Budgeted units will distribute the total units along the revised duration of the schedule.
3- The remaining units (early or late) shall distribute the difference between the actual units at a certain data date & the total remaning units.

Can u justify this?

Regards.

3 replies

Oldest first
  1. 0
    Nigel Hussey ·
    Yes and no, depends on some settings. check your "Admin Preferences" on "Earned Value" calculations and also check "Resource Assignments" settings against your specific project.
  2. 0
    Alex Wong ·
    Sorry dont really understand your question.

    "Can you justify this??" - Please explain a bit more

    Alex
  3. 0
    Karim Mounir ·
    Hi Alex,

    I meant to confirm these info.

    Regards.