Actual, Budgeted, Remaining Early & Late units
In the Open Standard
Karim MounirMember for 20 years 6 months
- Created
- 3
- 2
0
Hi,
I made a revised target schedule and i want to clarify some info here regarding the resource distribution (used in Tracking layout in p5):
1- The Actual units shall remain the same.
2- The Budgeted units will distribute the total units along the revised duration of the schedule.
3- The remaining units (early or late) shall distribute the difference between the actual units at a certain data date & the total remaning units.
Can u justify this?
Regards.
I made a revised target schedule and i want to clarify some info here regarding the resource distribution (used in Tracking layout in p5):
1- The Actual units shall remain the same.
2- The Budgeted units will distribute the total units along the revised duration of the schedule.
3- The remaining units (early or late) shall distribute the difference between the actual units at a certain data date & the total remaning units.
Can u justify this?
Regards.
3 replies
Oldest firstLog in or join to reply