Actual import
In the Open Standard
SA
Salman AhmedMember for 16 years 7 months
- Created
- 17
- 5
0
17 replies
Oldest first- 0APArnold Puy ·Hi Salman,
As I mentioned in my post #4 that you cannot modify the data with (*) next to column title in Excel, as unit % complete is one of them.
You need to do it in Primavera, by performing a global change. But be careful, always create a backup of your schedule prior to perform global change.
Regards,
Arnold
- 0APArnold Puy ·Hi Salman,
Are you talking about the Units % Complete? In this case you need to input your actual units manually to have your units % complete. Otherwise, do it in Excel by exporting your actual, remaining, budget & at completion units. For sure!!
If in case your physical % complete = units % complete then it is more easy to track. Can you elaborate in more detail.
Regards,
Arnold - 0RMRodel Marasigan ·Export & Import Data to Excel to update actual is required knowledge on how the Primavera database work to accept data. The import update will depends on your settings where normally comes to disappointing result if you don’t know what your doing. When updating TASKRSRC table using the Export/ Import Excel facilities check the settings on Calculation Tab Resource Assignments under Project Modules. When updating Actual Units or Cost, which one is tick? Is it Add actual to Remaining or Subtract Actual from At Completion? Next to check is a % Complete Type setting on each activities. Is it Duration, Physical or Unit?
Note: Activity % Complete and Performance % Complete is based on the % Complete Type settings. (i.e. if set to Duration then Duration % Complete = Activity % Complete = Performance % Complete, Physical then Physical % Complete = Activity % Complete = Performance % Complete and Unit then Unit % Complete = Activity % Complete = Performance % Complete)
Important fields to export and import:
1) Activity ID, Activity Status and WBS code for TASK or Activity update
2) Activity ID, Activity Status, WBS code, Role ID and Account ID for TASKRSRC or Resource assignment update.
If updating Task such as Activity code, WBS code, Activity Status, Actual Start and Actual Finish date, Physical % complete, Duration % complete, etc.. then TASK export is useful but not on units or cost if the update meant for resource.
Note: Importing Actual % complete update behaviour of Primavera will depends on the Duration Type settings and % complete type. Check synchronisation update for this settings on PM manual (i.e. Duration Type = Fixed Duration and Unit and % Complete Type = Duration then field to update is Duration % Complete only which will synchronise the update on remaining duration and actual duration using the calculation settings that I mention earlier. (i.e. subtract actual from at completion)
Start and Finish Status will be trigger by Activity status field. If the activity is 100% complete it can be done by changing Activity Status field = Completed (start and finish are both tick), started with or w/out progress = In Progress (Start is tick) and not started = Not Started (none are tick)
If updating units or cost to resources then TASKRSRC is the best export to use. Make sure to update the actual units or cost and also remaining units or cost. (this will calculate at completion units or cost and unit % complete.
Note: if the setting of resources is calculate cost from units then cost will be automatically update base on unit * price/unit and does not need to update costs fields.
Still lot of things needed to explain but it’s getting too long…
- 0SASalman Ahmed ·Thanks a lot Mr.Rodel,
Please let me know is there any way to have each coloumn for each resource, so that I can export the same and input the required resource units and import back.
Please suggest some easiest way to load multiple resoures & their buget values on each activity, instead going to each activity and adding the resoure and its budget values.
Thanks for your valuable replies. - 0RMRodel Marasigan ·There are many ways of loading or assigning resources. You can use resource assignment module and fill down (ctrl+e) for all the same resources or using ODBC database, SDK and or use the export/ import facilities etc… which ever is comfortable for you to use.
Steps in loading resources using excel SDK and excel Export/ Import facilities
1) Define/ create resources to use in the program.
Using excels SDK is more reliable and convenient way to use especially if your project required multiple or detail resources…(labors: i.e. name of each person).
Excel Export/ Import are not working properly especially if you have roles define or hierarchy. Another is the excel xerFileParser&Builder.xls (you can download it from Primavera knowledgebase)
2) Define rates per resources (again I suggest excel SDK). Excel export/import don’t have this function.
3) Export spreadsheet-(xls) Activities and Resources assignment.
-> Activities basic field required: Activity ID, Activity Status, WBS Code and Activity Name for your reference when adding resources on TASKRSRC tab. You can add more field if you required more reference.
-> Resource assignment basic fields: Activity ID, Activity Status, Resource ID, Roles ID, Cost Account ID, Budgeted Units, Remaining Units and At Completion Units.
4) Start assigning your resources by completing all fields required. If roles and cost account is not used then leave it blank.
Note: Caution: if assigned resources is existing on that activity id but roles is defined or cost account is defined on the existing but not on the new assignment, import will not update the existing resource instead it will add a new assignment specially if the setting on resources tab-> Resource Assignment (Resource assignment can be assigned to the same activity more than once) under Project module is tick. Also make sure that there is no duplicate resource id which is possible in P6 resource under different level on hierarchy. It may assign different resource than the intended resource.
Excel SDK is also another way of assigning resource but requires to write a program (Visual basic code) but more reliable because it deals with unique id which is not present in Excel Export/ Import spreadsheet.
Good Luck!!!
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?