How to show critical Path for an updated activitie
In the Open Standard
Haresh JayanthMember for 20 years 1 month
- Created
- 5
- 2
0
Hi Guys,
How to show critical path for an updated activites / already completed activities , when the project is in progress. to make my question clear i will given one example
Example
The substructure in a project is already completed. The balance is superstructure of the building. if i choose longest path it show critical path on balance activities ? My question is that how can i show critical path for activites which is already completed i.e. substructure as per the present progress of the site? Since the critical path may not be same when the critical activities are progressing ahead of schedule. in this case if i want to show critical path on already completed activites? How can i show it?
How to show critical path for an updated activites / already completed activities , when the project is in progress. to make my question clear i will given one example
Example
The substructure in a project is already completed. The balance is superstructure of the building. if i choose longest path it show critical path on balance activities ? My question is that how can i show critical path for activites which is already completed i.e. substructure as per the present progress of the site? Since the critical path may not be same when the critical activities are progressing ahead of schedule. in this case if i want to show critical path on already completed activites? How can i show it?
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?