Financial Periods

Dinesh KumarMember for 20 years 5 months
Created
2
2
0
Gents,

I’ve defined new financial periods (12 month periods for year 2007) in Primavera PM Ver 5.0. When I tried to assign one of this period to a Project, the newly defined ’financial periods’ were not available for assignment, instead the built in 2006 year ’financial periods’ were only available to choose from!!

Whether we have to assign the finacial periods to a project at EPS level? if yes, how? Please advise..

Regards,
Dinesh Kumar CM
dckumar@lamprell.com
Dubai

2 replies

Oldest first
  1. 0
    Paul Harris ·
    I do not quite understand your problem, but have you set the financial periods to view in the User Preferences, Application tab.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Dinesh Kumar ·
    Paul,

    Thanks, that solved the problem.

    Dinesh