Applying Progress to a Level of Effort Activity
In the Open Standard
Philip RichardsMember for 22 years 9 months
- Created
- 3
- 1
0
Can anyone please advise.
I am trying to update the ’Actual Units’ to a Level of effort activity in P5. Units go in ok, and Remaining units & percent complete do change accordingly, but when the project is re-scheduled, Actual units go back to zero.
I have Duration Type set to ’Fixed Duration & Units’ & Percent complete type set to ’Units’. There is no curve applied to the resource.
Regards
Phil
I am trying to update the ’Actual Units’ to a Level of effort activity in P5. Units go in ok, and Remaining units & percent complete do change accordingly, but when the project is re-scheduled, Actual units go back to zero.
I have Duration Type set to ’Fixed Duration & Units’ & Percent complete type set to ’Units’. There is no curve applied to the resource.
Regards
Phil
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?