How can i add a new data base for P6.V7

Forat FarisMember for 20 years 2 months
Created
12
2
0
Dear all
Greetings,
How can i add a new data base for P6.V7 ?
Before in p6.1 we had the file (ConfigAsst)..but here nothing..
Hoping for your help.
Thanks

12 replies

Oldest first
  1. 0
    Ronald Winter ·
    Forat,

    If you are using an Oracle database, then the answer is easy; there is no way to add a new database. Oracle only supports one database per server (or machine). Only MSSQL and SQL Express support multiple databases. Good luck!
  2. 0
    David Smith ·
    The utility still exists. It is now called DBSETUP.BAT and is still located in /install/database/.

    The terminology is different in Oracle. What MS SQL calls a "database" is called a "Schema" in Oracle.

    You can have multiple schemas, however I do not recommend it with the Oracle XE that comes with Primavera. If you have a full Oracle server you can change the logins such as: ADMUSER_NEW, PUBUSER_NEW, PRIVUSER_NEW. Use the new logins you created in the wizard when setting up your Alias.

  3. 0
    Forat Faris ·
    Dear friends Ronald&David
    Thanks a lot for your replies…
    Daer David
    Iam using MSSQL …
    I tried to use (DBSETUP.BAT) ,but after two steps , coming this window
    DBA user name--------------------sa
    DBA Password ---------------------(Required)
    Database host address-------------My name
    Database host port -------------- 1433
    After entering the DBA password ,an error massage coming { SQL Server Exception : The TCP/IP connection to the host (Myname) ,port 1433 has failed :"connection refused)………….."}

    regards,


  4. 0
    Rodel Marasigan ·
    Forat,
    Database host port - 1433 is Primavera default but may not always the case a correct port and depends of what the PC assigned to your Primavera TCP address. To check the correct TCP address you have to goto Start-> Run-> Regedit and find this address:
    HKEY_LOCAL_MACHINE\SOFTWARE\Microsoft\Microsoft SQL Server\PRIMAVERA\MSSQLServer\SuperSocketNetLib\Tcp\TcpPort then use that address when adding new database.

    Best Regards,
    Rodel
  5. 0
    Forat Faris ·
    Thanks a lot Rodel....
    but also not working
    i got the new port =49701 ,
    i changed the old one 1433 with 49701
    the new massage is:
    SQLServerException Login failed for user ’sa’
  6. 0
    Rodel Marasigan ·
    Forat,
    Can you check again the TCP. It’s normally 4 numbers.
    Also make sure the login are:

    usersname: sa
    password: Prima123Vera

    Good Luck!!!

    Best Regards,
    Rodel
  7. 0
    Forat Faris ·
    Thanks again Rodel..
    Not working again
    i allowed to myself to send you an excel file showing my settings..
    Best regards
  8. 0
    David Smith ·
    If it is a stand alone installation. The host name should be:
    \PRIMAVERA or simply LOCALHOST\PRIMAVERA

    The stand alone installation creates a named instance (PRIMAVERA) so you must include that in your database host name.

  9. 0
    David Smith ·
    Correction: YourComputerName\PRIMAVERA
  10. 0
    Forat Faris ·
    Thank you david
    it is working now ,
    the corrected settings are :
    DBA user name--------------------sa
    DBA Password ---------------------Prima123Vera
    Database host address-------------LOCALHOST\PRIMAVERA
    Database host port -------------- 49701 (Based on Rodel Instructions above)
    New problem coming :after reaching (creating database )
    first step :Create the PMDB tables ---------------ok
    second step :Load sample data------ coming this massage :
    "Error in Load data from datasource SAMPLE:pmdb_ec_empty.zip : DatabaseToolException (Value not of a valid date string. Type is YYYY-MM-DD HH:mm:ss.s)"

    thanks a lot
  11. 0
    Jas Thak ·

    Is it possible to load

    Is it possible to load activities in P6.V7 to Oracle data base ?

    If so, please explain how can it be done.

     

    Thanks  jasthak

  12. 0
    Antonio Palomar ·

    if we cannot add new data

    if we cannot add new data base in P6 v7, how can we un-instal it so we can install a new one