Removing actual, Suspend and Resume Dates

James bidMember for 17 years
Created
4
2
0
Hi Guys,

I have three activities in my program that i want to remove the actual dates, suspend date and resume date.
For actual dates, i tried to remove the actual units, set OD to zero but still i can’t remove the actual date.
Hoping for your help.

Thanks

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Christopher,
    Change the actual units to 0 first before you can remove actual dates.
  2. 0
    James bid ·
    Thank you Rodel for immediate response.

    I tried also to set the actual units to zero but still, \i can’t remove the actual date. Any other remedy?

    Also, please help me to remove the suspend and resume date.

    Regards.

    Chris
  3. 0
    Rodel Marasigan ·
    Christopher,
    To remove Suspend and Resume date, highlight suspend date and press delete on keyboard.

    To remove Actual date go to Activity detail Resource tab and change to 0 all resources assigned then un-tick start date.

    You can also use global change for both queries.

    Best Regards,
    Rodel
  4. 0
    James bid ·
    I got it.

    Thanks Rodel for your help.

    Chris

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?