Percent Complete
In the Open Standard
Philip RichardsMember for 22 years 9 months
- Created
- 4
- 1
0
Can anyone explain why in P5 (and P3), duration percent complete is calculated using ’Original Duration’ (OD-RD)/OD.
Should it not be based on ’At Complete Duration’.
As it is, where an activity has started, (and so has an ’Actual Duration’) but the ’Remaining Duration’ is greater than the ’Original Duration’, the % complete = 0. Surely this cannot be correct.
Is there an option anywhere to re define the calculation, or ideally to re-set the Original Duration to equal Actual + Remaining?
Should it not be based on ’At Complete Duration’.
As it is, where an activity has started, (and so has an ’Actual Duration’) but the ’Remaining Duration’ is greater than the ’Original Duration’, the % complete = 0. Surely this cannot be correct.
Is there an option anywhere to re define the calculation, or ideally to re-set the Original Duration to equal Actual + Remaining?
4 replies
Oldest firstLog in or join to reply