how can i run apply actual
In the Open Standard
Tamer SayedMember for 20 years 8 months
- Created
- 1
- 2
0
in p3 there are update progress to know how much percentage we will do in specific day and make compareson with that dan in actual to know that we are advanced or dalay ???
in p3e as my knowlage the same option is apply actual from tools
or this are no relation between both
also when i run tpply actual and put date it shuld give me percentage i have to do in this date
but i fould the following :-
all project turn to that date
example
first date is 1/1/2007
and i want to know what i will do in 4/1/2007
so i go to tools and apply acutal and put date 4/1/2007
and make compare with actuals
but after i run apply actual in day 4/1/2007
all project turn to 4/1/2007
that is mean first date will be 4/1/2007
atherwiset the original first date i put before 1/1/2007
in p3e as my knowlage the same option is apply actual from tools
or this are no relation between both
also when i run tpply actual and put date it shuld give me percentage i have to do in this date
but i fould the following :-
all project turn to that date
example
first date is 1/1/2007
and i want to know what i will do in 4/1/2007
so i go to tools and apply acutal and put date 4/1/2007
and make compare with actuals
but after i run apply actual in day 4/1/2007
all project turn to 4/1/2007
that is mean first date will be 4/1/2007
atherwiset the original first date i put before 1/1/2007
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?