hoe can i use fill cell in P3E

Tamer SayedMember for 20 years 8 months
Created
5
4
0
there are fill cell in P3 if i want to put the same duration in many activities so i hilight for duration cells and right click and press to fill cell
duration appear automatic in all activities
my question now how i use the same option in P3E
or where is fill cell in P3E
thank you

5 replies

Oldest first
  1. 0
    Oliver Melling ·
    Tamer,

    Select the item you want to fill down with the left mouse button, then hold down control and shift, then select the last activity you want to fill down to with the left mouse button. (This should highlight all the activities you wish fill.)

    Next press the right mouse button and select fill down.

  2. 0
    Santosh Bhat ·
    Its used exactly the same way as in P3. Either right click, or on the EDIT menu.
  3. 0
    Mangesh Khuspe ·
    tamer

    it is by name of "fill down" in edit menu.


    regards
    mangesh
  4. 0
    Marcio Sampaio ·
    Choose the cell that has the information that you desire to place in all the other cells, select it and all the others that you want to modify and then fill cell.

    Regards.
  5. 0
    Suresh Sankarankutty PMP ·
    Tamer
    click in the first cell from where you want to fill , select until the cell you want to copy Eg: Activity id 10010 to 10090 then press Ctrl+E . Hope you found useful.
    Suresh