Converted Data P3x to P5 _ Not correct

Zq qzMember for 23 years 4 months
Created
2
2
0
Need urgent Help.......

I’m trying to convert P3.1 schedule to P5, but budget quantity data change (All data multiplied by 8) why????

How to do this using prmconvert.ini

FM

2 replies

Oldest first
  1. 0
    Miguel Angel Fopiani Bernal ·
    Hello,

    The reason for this conversion is because while P3 planning base was daily, P5 is hourly.

    Therefore as default any resource without unit declared in P3 will be multiplied by 8.

    But this situation can be solved if you enter a resource unit in the resources window, then if you state a unit like h, hr, etc P5 during normla importation will consider that these resources are already in a hourly base and will not multiply.

    This is the best solution that I can give you at this moment. I am checking the posibility to consider blank units as hourly units through modifiying the PrmConvert.ini file. If a get something I will post it here.

    Regards

    Miguel
  2. 0
    Alex Wong ·
    another easy solution

    run a global change to

    OD = OD /8
    BQ = BQ /8

    if that is the only different

    Alex