Can anyone help me please.

I am trying to familiarise my with P3e.

Please advise - after resource/cost loading been done, how to import datas for monthly/weekly distribution in excel.

To see earned value on the screen while updating, in update what percentage update to be used (unit % or physical %).

Please tell me the basic difference between P3 & P3e briefly.

I would appreciate your feedback

1 reply

Oldest first
  1. 0
    Dinesh Kumar Damavarapu ·
    Hi Goutam,

    How are you?

    easiest way to get time spread data to excel is going to the resource assignment view>select the required resource or information you needed>select month or week>go to edit> select all or select the necessary item> copy> and paste in Excel.

    Cheers.

    Dinesh