A quick response needed!
In the Open Standard
Oliver MellingMember for 19 years 5 months
- Created
- 11
- 4
0
All,
Assuming I have used two different calendars for activities in a programme.
i.e
1. an installation team working 40 hrs/ 4 day week.
2 site mangement team working off-site 37.5 hrs/ 5 day week.
the duration shown in the ’original duration’ column changes depending on the number of hours stated for a standard day in admin preferences.
(5 days in the 37.5hr/week calendar appears as 3.75 days when the admin preference is set as 10 hours/day)
Is it possible to show the duration in relation to the activities calendar?
Cheers
Assuming I have used two different calendars for activities in a programme.
i.e
1. an installation team working 40 hrs/ 4 day week.
2 site mangement team working off-site 37.5 hrs/ 5 day week.
the duration shown in the ’original duration’ column changes depending on the number of hours stated for a standard day in admin preferences.
(5 days in the 37.5hr/week calendar appears as 3.75 days when the admin preference is set as 10 hours/day)
Is it possible to show the duration in relation to the activities calendar?
Cheers
11 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?