Database lost, import not working urgent help needed
- Created
- 9
- 5
Hi Guys
Im knee deep in it with bosses breathing down my neck so im really hoping somebody can help me
here the history
1) ive just taken over from a planner on a very big project that is 70% complete
2) I took over his notebook with primavera on and all the sites programs etc
3) The Laptop is on a network so the IT guys at headoffice changed the computername and then
primavera freaked out, could not open the database
4) They tried to fix it and somehow managed to delete the entire backup of the database
5) The notebook is still at headoffice as im working 400km away
6) I installed primavera on my personal pc to try and carry on with work
you guy can see what predicement i am in :( all i have is one baseline.xer file and a the last update.xer that i found on the previous planners sent items in outlook
I imported the update but for some or other reason most of the figures went haywire, the total float shows allot more than it was and the performance complete went up couple % by its own, the schedule % complete looks correct
I then assigned a baseline prog, the base i found on his mail and nothing much changed.
thank you in advance
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
IT experts, you do not need them ...................................