User Monitoring in P5

Robin KilmisterMember for 19 years 6 months
Created
1
1
0
Hello Planners,

I have jsut assisted in the migration of our P5 from stand alone computers to a network database. I have since found that if another user is in looking at the same project that I am working on I get a warning note appear when I schedule.
I can see from ADMIN - USERS - LOGGED IN column who is logged on the PMDB server but not which projects individuals are working on.
Is there a way to see which project is currently opened by which user? Or What each user has open?

Thanks for taking your time to consider my issue.

Regards

Robin.

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Robin

    File --> Open --> 1! click on the project or the area, you want to check --> Click onto the button "User" on the right side of this window. Now you see all users who opened projects in this area and with wich mode the are working.

    Regards
    Dieter