Steps - User defined text

Haresh JayanthMember for 20 years 1 month
Created
11
8
0
I have inserted a column in Steps tab, User_text1 and typed some text messages.

Later , when i inserted a column namely User_text1, the typed matter is not reflected in the column. So i want to exactly know, where all the matter , i have typed is stored, if i am typing in the steps tab, user_text1 columns.

11 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    Step is a production step to measure progress using Physical % complete and nothing to do with user define field. You can create a steps template that can assign to every activity or manual step per activity.
  2. 0
    Haresh Jayanth ·
    Dear Rodel,

    I know steps have nothing related to user defined text. My question was , we can insert a column called user defined text in Steps tab (right click customize steps column and insert user_text1 column).

    But When we type any text in user defined text, the same should be reflected on the activity table when we insert a same user defined column for eg user_text1.

    The User defined inserted column, shows blank, what may be reasons for the same.........
  3. 0
    Rodel Marasigan ·
    Haresh,
    I don’t know if you can insert user define text in Step tab. It has a fixed field called as follows:
    Step Name
    Step % Complete
    Step Weight
    Step Weight percent
    Completed

    There is no user define text. I haven’t encounter any user define in Step from P4 to P6.2 v7
  4. 0
    Haresh Jayanth ·
    Dear Rodel,

    Apart from this fixed fields , you can also insert userdefined fields , click on steps tab, right click inside the steps, goto customize step columns, you can see in available options , two category General & Userdefined.
    Click on Userdefined and select user_text1.

    And type any text in that column.....I want to know where it is getting saved. How to see this column in Activity table???

  5. 0
    Rodel Marasigan ·
    Haresh,
    You can only have user define field on Steps if you define users define field under Activity Steps. Is that what you talking about? From the Step tab you cannot define user define field itself.
  6. 0
    Haresh Jayanth ·
    Rodel,

    I have defined user defined field in steps, and typed some description on user defined field, but when i inserted a column "User defined field, in Activity table ,the said area is showing blank??

    Why this area is showing blank , even after defining it.....
  7. 0
    Rodel Marasigan ·
    Haresh,
    Do you mean that you define a users define field on Activity Steps? (Enterprise-> Users define fields-> Activity Steps) Is that what you querying about?
    UDF Steps
  8. 0
    Haresh Jayanth ·
    a) Enterprise,userdefined, activity steps...

    Yes....I have already defined user_text1 in activity steps after going to enterprise , userdefined and activity steps.....

    b) Steps tab:

    I have typed some texts (instead of notes), by going to steps tab after inserting a column "user_text1".

    c) Activity table:

    This typed text is not visible when i insert a column "user_text1 in activity table....

    Any reasons...
  9. 0
    Rodel Marasigan ·
    Haresh,
    If you define a UDF under its category it will be available only on the category that you selected.
    Ex: UDF Activity = Activity table
    UDF Project = Project table
    UDF Resource = Resource table
    UDF Activity Steps = Steps table
    UDF Risk = Risk table
    UDF WBS = WBS table etc... etc...
    It’s same as Activity Code, Project Code and Resource Code.
    There is no way you can use UDF Steps in Activity table as it has own UDF. YOu may use the same UDF name i.e. User_Text1 but they are different table.
  10. 0
    Haresh Jayanth ·
    Correct...thanks

    One more out of context question.......How do you insert any images, in your post , at the time of replying or posting questions....

    I still dont know , how to insert a image in post.....

    regards,
  11. 0
    Rodel Marasigan ·
    Haresh,
    You need an image host(i.e. friendster, facebooks, photobuckets...etc) and use html code to insert images.