Using P3e I’d like to produce a stacked resource histogram displayed by each project. Currently I assign a resource accross multiple projects & would like to be able to see the cumalitive loading on a per project basis. I have been advised that this is possible but I can’t find a project filter to apply in my filtering option.

I am also having trouble naming & changing the X & Y axis information in the graphs.

2 replies

Oldest first
  1. 0
    Andrew Dick ·
    Mark, this is very possible ith the My Primavera add on, I’m currently doing this in the assignments view with a spreadshet, as this is how my resource managers like to see things. I haven’t tried the stacked histos in the client, but will be very interested in further posts here.

    Andy
  2. 0
    Khuong Do ·
    Hi Mark
    You must use myPrimavera Resource portlet to produce this kind of report.
    In Resource portlet choose Resource Analysis. On Chart Type choose Stacked Histogram.
    Then choose the resource you want and it will show resource loading grouped by project.

    Thanks
    Khuong