where to find P3e API

Zhang HaixiangMember for 21 years 6 months
Created
3
1
0
Hello,

Before I’m using P3, and have written some codes using RA in EXCEL.

Now our company is shifting to P3e, does it also have a API?
where can I find information e.g. description of object model/method/property and sample code?


thanks in advance

3 replies

Oldest first
  1. 0
    Arthur Godbeer ·
    Yes. There are two APIs, the original one is ODBC-based and the newer one is XML (Java). There is full documentation on the API CD that is one of the supplied CD set. But to use the XML API you have to be licensed. At present there is no Primavera charge for that. But your licence file will have to be updated and your Primavera representative will have to order that update for you.
  2. 0
    Zhang Haixiang ·
    Hi,

    thanks for reply.

    I ’ve 3CDs of P3e, I can not find the XML API.

    and i have installed primavera SDK, is that the ODBC-based API?


  3. 0
    Arthur Godbeer ·
    In my experience, P5 and P6 were/are always delivered with four CDs. Perhaps it is different in China, check with your Primavera rep.

    Yes, that installation would be the ODBC API. It will work, the main differences compared with the XML one would be the slower speed when very large amounts of data are being transferred, and that it requires the likes of C++ or VB programming compared with Java. (Although I was a programmer many years ago, I don’t have experience using either API.)