Hi everyone - I’m a very new user of P3e, and am hoping for a bit of advice please.

I want to set a bar with individual markers for monthly meetings, instead of one long bar. Is this possible in P3e and if so, how???

4 replies

Oldest first
  1. 0
    Oliver Melling ·
    Sarah,

    Meetings can be planned in 2 ways.

    1* With the budget against a ’Level of Effort’ activity. This means that when the data date moves along you will automatically claim performance against the budget you set aside for meetings.

    2* As meetings are individual tasks, you can insert an activity of 1 day duration (or whatever duration the meeting will be) for each meeting you intend to hold. This will give you a chain of meetings driven by lag relationships (i.e. bi-weekly meetings) or by other activities in the programme. You can also split one activity into sperate parts.

    Have you done any formal training on P3e yet?

    Oliver
  2. 0
    Sarah Henderson ·
    Thanks Oliver for the reply.

    I’ve only done on-the-job training, working from a manual which we happen to have in the office. The programme I am trying to create is only for visual effect, to be included in a bid we are tendering. I was hoping to be able to provide a linear chain of meetings on one line called "bimonthly meetings" rather than a visual staircase of linked meetings. I thought I had seen this effect on other plans, and presumed I could do it in P3E. Apparently not!
  3. 0
    Susan Young ·
    If you are looking for a visual effect then there is a possibility by following steps:

    1) Create a seperate WBS level where u wish to have the activity titled " bimonthly meetings"
    2) create a "Level of Effort" activity called Bi weekly meetings
    3) Add milestone activities for all dates you expect meetings to be held & link it suitably to LOE activity.
    4) Under bar settings for LOE activity & milestones, Check "show bar when collapsed"
    5) Schedule & minimise the WBS.

    You should be able to see a long bar with milestones superimposed.

    Hope it helps

    Sue
  4. 0
    Sarah Henderson ·
    Sue, I owe you chocolate - that worked a treat!

    Thanks ever so much...I would NEVER have figured that out on my own.

    Regards,
    Sarah