Skip to content

DO I APPLY ACTUALS TO GET ACTUAL ????

Suresh Sankarankutty PMPMember for 20 years 2 months
Created
4
2
0
Hi
Anyone have any idea how to get the Acutals Labour Unit without apply actuals. I set up my project with % Complete type as Duration and i do not "Apply Actuals". But i want to look at the actual labour units when the job finish. Is there any idea ???

Another problem i face is, When i schedule the job every day, those job which are Not Started accordingly (BL Start) eg: BL Start date is 17-09-07
Data Date is 18-09-07 . When schedule this job on 18.09.07 all job which were suppose to start on 17-09.07 and if not started, all those activities will be jump to 18.09.07. I dont want that. I hope if i apply actuals the planned date will remain same. Is’nt it ?
Is there any idea ???

Regards
Suresh

4 replies

Oldest first
  1. 0
    Anoon Iimos ·
    yes of course, just make sure you got your target before applying actuals
  2. 0
    Dieter Wambach ·
    Hi Suresh

    Data Date is one of the most important date of your schedule: all events before DD DID happen, all events on or later than DD are planned.
    If you have an activity planned for (early start) Sep. 17, no actual start exists, and your DD is Sep. 18, the earliest possible start is Sep. 18 - thus early start will be Sep.18 after F9.
    DD always is the status of your project’s actuals. I assume that the status of your project is not Sep 18, but an earlier date. So set DD to an earlier date and it will be ok.
    Regards
    Dieter
  3. 0
    K D ·
    Hi.
    If you set "Duration" in Complete type and check "Auto compute actual" option in resource definition, your actual labor unit/cost will automatically calculated based on Duration % complete.
    Then you do not have to use "Apply actual" function or Timesheet.

    Thanks
  4. 0
    Oliver Melling ·
    Suresh,

    You must save a copy of your plan, then assign it as a baseline.

    This way the baseline planned dates will stay the 17th September and when the data date is moved your current plan will say 18th September.

    Comparing the two plan allows EVA.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?