DO I APPLY ACTUALS TO GET ACTUAL ????
In the Open Standard
Suresh Sankarankutty PMPMember for 20 years 2 months
- Created
- 4
- 2
0
Hi
Anyone have any idea how to get the Acutals Labour Unit without apply actuals. I set up my project with % Complete type as Duration and i do not "Apply Actuals". But i want to look at the actual labour units when the job finish. Is there any idea ???
Another problem i face is, When i schedule the job every day, those job which are Not Started accordingly (BL Start) eg: BL Start date is 17-09-07
Data Date is 18-09-07 . When schedule this job on 18.09.07 all job which were suppose to start on 17-09.07 and if not started, all those activities will be jump to 18.09.07. I dont want that. I hope if i apply actuals the planned date will remain same. Is’nt it ?
Is there any idea ???
Regards
Suresh
Anyone have any idea how to get the Acutals Labour Unit without apply actuals. I set up my project with % Complete type as Duration and i do not "Apply Actuals". But i want to look at the actual labour units when the job finish. Is there any idea ???
Another problem i face is, When i schedule the job every day, those job which are Not Started accordingly (BL Start) eg: BL Start date is 17-09-07
Data Date is 18-09-07 . When schedule this job on 18.09.07 all job which were suppose to start on 17-09.07 and if not started, all those activities will be jump to 18.09.07. I dont want that. I hope if i apply actuals the planned date will remain same. Is’nt it ?
Is there any idea ???
Regards
Suresh
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?