Hello guys,

can anyone tell me is there any way to give password to PRX file or P3 file

rajesh

2 replies

Oldest first
  1. 0
    Karim Mounir ·
    Not possible, u can only put restrictions or access rights from within P3.
    If u want to put a password on the prx file, u have to compress it and put a password through the compression software (winzip or winrar).
  2. 0
    Mk Tse ·
    alternative

    In P3, assign the project to a particular user only, remove all the rest users including "everyone" then backup the project into PRX with option "NOT remove" access right.

    Only assigned user can open the file.