Budgeted Cost being Recalculated
In the Open Standard
Mark ChapmanMember for 20 years 5 months
- Created
- 3
- 3
0
I’ve added a budgeted cost to a resource and this is spread linear. The resource histogram shows this is fine. However, I have done a few things (change spreadong curve and run the "recalculate assignment costs" and suddenly the budgeted cost is zero. Why is this? The "Calculate costs from units" is unchecked.
This work has been sub-contracted out and thus includes not only resource costs but also materials. Should I use non-labour, materials, expenses or labour? What should I do with units? Make this zero?
Cheers,
mark
This work has been sub-contracted out and thus includes not only resource costs but also materials. Should I use non-labour, materials, expenses or labour? What should I do with units? Make this zero?
Cheers,
mark
3 replies
Oldest firstLog in or join to reply