Adding steps (by external means)

Jerry LanMember for 20 years 1 month
Created
14
5
0
Hi fellow planners,

Is there a way to import "Activity Steps" from excel into an activity in P5? I am not referring to using already saved "Activity Steps Templates".


Kind regards,
-j- erry

14 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Jerry
    It should be possible by the programming interface API. I don’t know a different solution.
    Regards
    Dieter
  2. 0
    Rodel Marasigan ·
    Jerry,

    Are you refering to create an activity steps group added to templates or assigning activity step into activities? Or both?

    There are 3 tables in PMDB database related to that exercise which are PROCGROUP, PROCITEM and TASKPROC. You can update these tables using SDK or ODBC link or just a simple update from XER.

    Should you require assistance, send me a PP with your email address so I can assist you step by step.

    Regards,
    Rodel
  3. 0
    Jerry Lan ·
    Thanks for the help!

    What is API? My intention, let’s say, to illustrate, is to have all items to be procured as steps for activity name "Procurement of piping". Now my procurement department has in excel format all the piping items to be procured. In this way, we can just check when that item comes and we get the % progress. Hope this clarifies. Where can I find these files or exercises, Rodel?

    Kind regards,
    -j- erry
  4. 0
    Rodel Marasigan ·
    Jerry,

    API means Application Programming Interface. SDK is a sidekick that you can use to have link access your PMDB database which included in your P5 cd’s installation disk. You did not include your email address for much better communication.

    Regards,
    Rodel
  5. 0
    K D ·
    Hi Jerry.
    We think you can use the excel macro tool to import activity step.
    You can download that free tool at Primavera POINT website.

    Thanks
  6. 0
    Jerry Lan ·
    Hi K D,

    I could not find the excel macro tool on the Primavera POINT website for download. Could you help me out with the link?


    Kind Regards,
    -j- erry
  7. 0
    K D ·
    Hi Jerry.
    You can search for this solution ID : prim4617

    Regards
  8. 0
    Jerry Lan ·
    Hi K D,

    This "activity5x" file does seem very neat!! I have never used SDK before. Is it I click on "Set Activity Steps" and my P5 schedule gets updated real time? That sounds too good. Unfortunately my SDK or API (sorry I do not really know the difference), it does not seem to be working. Any help on how I can get it to be working is appreciated, if this SDK/ API is what I understand it to be. After I installed API from the API cd, it seems nothing happened, except that now I have a program file "API". Is it I need to be a superuser or higher to be able to use it? Thanks so much K D!

    Regards,
    -j- erry
  9. 0
    Jerry Lan ·
    Hi K D,

    This "activity5x" file does seem very neat!! I have never used SDK before. Is it I click on "Set Activity Steps" and my P5 schedule gets updated real time? That sounds too good. Unfortunately my SDK or API (sorry I do not really know the difference), it does not seem to be working. Any help on how I can get it to be working is appreciated, if this SDK/ API is what I understand it to be. After I installed API from the API cd, it seems nothing happened, except that now I have a program file "API". Is it I need to be a superuser or higher to be able to use it? Thanks so much K D!

    Regards,
    -j- erry

    p.s error message: "Row 0: rosoft][ODBC Driver Manager] Data source name not found and no default driver specified"
  10. 0
    Dieter Wambach ·
    Hi Jerry,
    SDK and API both are programmers’ tools. Both work with the database directly - so no control on correct entry. You need some programming experience to use them. Be careful!
    The error message gives a hint: the file name was wrong.
    Sorry for being very direct
    Dieter
  11. 0
    K D ·
    Hi Jerry.
    In Excel tool there is 2 button : Get activity step and Set activity step. You use "Get" to get information from database to Excel file. After finish editing in excel file you use "Set " to update changes you made to database.
    You have to install SDK prior to use macro tool (Excel). You can find the way to install SDK in POINT.

    Thanks & regards
  12. 0
    Jerry Lan ·
    Thanks KD!!

    I will get my IT guy to install the SDK for me.


    Dieter,
    Thanks for the warning! I hope it will work.Clicking "get" and "set" seem pretty straightforward. I will make a copy of the project before importing. If it does not work, it will affect only the open project right? not the whole system.


    Regards,
    Jerry
  13. 0
    K D ·
    Data affected by the tool depends on which project you choose to loading in drop-down list box when you open the excel tool.
  14. 0
    Jerry Lan ·
    Thanks so much KD!

    It worked!!



    Gratefully,
    -j- erry