Hi all,

I am trying to work out the Planned Progress for turnaround doc.by P5 .

I got Baseline . For example , DD is 13th Oct and I want to find out the planned progress for 20th Oct .

Can anyone please tell me what should I do? Which column should I choose? Or is the same method to work out the planned progress for different % complete type like physical or units %?

Appreciate your help in advance

1 reply

Oldest first
  1. 0
    K D ·
    Hi Yao.
    We think you can copy that project to a different EPS and set the new one to what-if status.
    Update process on what-if project, if DD is 20-Oct than you can see the "schedule % complete".
    Am I understand you query correctly? not sure. :-)

    Thanks