Update Progress - Problem with actuals
In the Open Standard
Mark ChapmanMember for 20 years 5 months
- Created
- 7
- 2
0
I have noticed a problem in P5 that didnt exist in P3.
Each week/month I update the plan. I drag Progress spotlight (PS) to the new data date. There will be 3 types of activties (to simply things I have ignored the start date - assume all activities have started):
1. Those that are planned to finish within the window and do.
2. Those that are planned to finish within the window and don’t.
3. Those that are planned to finish outside of the window and now finish within.
I make changes to the activities where required. The bug I have found is those that come under No.3. In this case I drag the activity end date to within the SP window and then tick the AF box within the status tab.
After all the manual changes I then use the "Update Progress" option but this moves the activities in 3 to not complete.
What is happening? This worked in P3. Now using P5 SP4
Each week/month I update the plan. I drag Progress spotlight (PS) to the new data date. There will be 3 types of activties (to simply things I have ignored the start date - assume all activities have started):
1. Those that are planned to finish within the window and do.
2. Those that are planned to finish within the window and don’t.
3. Those that are planned to finish outside of the window and now finish within.
I make changes to the activities where required. The bug I have found is those that come under No.3. In this case I drag the activity end date to within the SP window and then tick the AF box within the status tab.
After all the manual changes I then use the "Update Progress" option but this moves the activities in 3 to not complete.
What is happening? This worked in P3. Now using P5 SP4
7 replies
Oldest firstLog in or join to reply