Showing numbers on Manpower Graph bars

Ijaz AhmadMember for 20 years 3 months
Created
3
3
0
Hi guys,
I am struggling to display the bugeted hours / no. of men on each bar of manpower histogram bars, but in vain. Although it gives the number when we double click on each bar, but I want to get the numbers displayed on each bar so that I can print the graph with the numbers on each bar.
Can anybody help me in this regard. It will be highly appreciable.
Thanks
Ijaz

3 replies

Oldest first
  1. 0
    Johny Kesserwany ·
    Hi Ijaz,

    It seems that we can’t !!! I already raised the issue with Primavera technical support and I wasn’t able to display the values on the bars....

    regards
    jk
  2. 0
    Waseem Saber ·
    Ijaz,

    this question has been raised with Primavera, this should be covered in P7 version "fingers Crossed", if you are so desperate, i would advice to export the data to any db and present your schedules....... this is more userfriendly and more graphical options..

    cheers

    Waseem Saber
  3. 0
    Arslan Usmani ·
    Ijaz,

    what we are doing is that from Resource assignment we transfer the data to Excel and plot the graph. This gives the room to plot the graphs on two vertical axis.

    Cheers,

    Arslan Usmani.