How to divide a task in several parts?

Horlen AstudilloMember for 18 years 9 months
Created
4
4
0
Hello I would like to know how to divide a task in several parts.

I had done it in Ms Project. But never in Primavera.

Could somebody help me, I am using P5

Regards,

4 replies

Oldest first
  1. 0
    Andrew Dick ·
    Horlen,
    In a nutshell, what you can do is create ’Steps’ within the activity in question giving weights to each step proportionate to the effort required of the total budget.

    Or if you need to divide the activity into discrete parts so that you can either add logic or divide the costs up, you will need to create ’New’ seperate tasks and budget them accordingly, (rebasline those activities if your baseline is at that level too)

    My thoughts
    Andy
  2. 0
    Sean Moghimi ·
    Horlen,

    Not sure about P5 as I can not rememeber but in P6 in the activity form you can use suspend option to break an activity but only for once. It might be the same in P5.

    For more breaks, I’m afraid you will need to add multiple activities.

    HIH,
    Cheers.
  3. 0
    Johny Kesserwany ·
    The feature to split task in MSP does not exist in Primavera. You have to go by adding several activities...

    JK
  4. 0
    Ferdinand U. ·
    there is a post in P3 forum where one planner suggests that using multiple holidays calendar be assigned to the activity, but during update it will not be accurate. you try..