using actual data files for new projects
In the Open Standard
Shiv RaoMember for 18 years 7 months
- Created
- 5
- 3
0
Presently i am working for an project where i have to use the existing file of client in Primevera 5 .0 .
This files are having actual data. And its Resource loaded.
No Baseline File exist that i can use .
the Only solution i think i have is to use this files.
[ If you have any other solution let me know]
The way i am moving forward is by :
Step 1 : Removing actual labor units = 0
Step 2: removing the activity status to not started .
But when i am doing this the Original Duration of the Activities are getting back to ’0’ , not only that the resources if are in multiple the duration is becoming 1 with varied duration for each resource.Which is more confusing.
I have checked with many of my other frineds , we are not able to get solution .
This files are having actual data. And its Resource loaded.
No Baseline File exist that i can use .
the Only solution i think i have is to use this files.
[ If you have any other solution let me know]
The way i am moving forward is by :
Step 1 : Removing actual labor units = 0
Step 2: removing the activity status to not started .
But when i am doing this the Original Duration of the Activities are getting back to ’0’ , not only that the resources if are in multiple the duration is becoming 1 with varied duration for each resource.Which is more confusing.
I have checked with many of my other frineds , we are not able to get solution .
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?