Reports in P6
In the Open Standard
Shareef Abdul AzeezMember for 21 years
- Created
- 8
- 4
0
Hello,
Can any one tell me how I can generate a Cash Flow report from P6.
In P3 I had the option of either using the Graphical reports and generate or use tabular report to get the spread in excel and the manually generate a curve.
How can i do this in P6.
I tried using export function into XLS type where I used ’Expenses’ but my export file is empty...Where did I go wrong.
My next doubt is when I enter a material resource for example in my project I have 8 bridge bearings each say 10,000$, totally 80,000$. Now to get this amount in the cost should I enter the budgeted units as 8...?(ie, 8 X 10,000$ =80,000$)???(as I have noticed that bugeted units, remaining units/Time are time realted and depend on my duration)
I tried to enter the budgeted amount (material cost) manually as 80,000$ but on recalculation this figure turns back to 0 ???
Can any one tell me how I can generate a Cash Flow report from P6.
In P3 I had the option of either using the Graphical reports and generate or use tabular report to get the spread in excel and the manually generate a curve.
How can i do this in P6.
I tried using export function into XLS type where I used ’Expenses’ but my export file is empty...Where did I go wrong.
My next doubt is when I enter a material resource for example in my project I have 8 bridge bearings each say 10,000$, totally 80,000$. Now to get this amount in the cost should I enter the budgeted units as 8...?(ie, 8 X 10,000$ =80,000$)???(as I have noticed that bugeted units, remaining units/Time are time realted and depend on my duration)
I tried to enter the budgeted amount (material cost) manually as 80,000$ but on recalculation this figure turns back to 0 ???
8 replies
Oldest firstLog in or join to reply