Levelling Roles

Oliver MellingMember for 19 years 5 months
Created
2
1
0
Does anyone know if it is possible to level Roles in P5?

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Oliver
    As far as I know it is not possible.
    Regards
    Dieter
  2. 0
    Andrew Dick ·
    Can’t be done.

    P6 has an extra peice of functioality where by you can manually set the total availability of the roles, similar to resources, max units time.

    Andy