P5 Auot arrange - Need to turn off.

Stormy J SummersMember for 19 years 10 months
Created
3
3
0
Could anyone help with turning the "autoarrange" function off in P5? When I enter a new code value for an activity, the activity jumps to another location w/in the schedule.

3 replies

Oldest first
  1. 0
    Dave Dodds ·
    From the sounds of it you are grouping by the code you are entering. This will always "autoarrange". If by entering the new code, the activity moves to somewhere you don’t want it, then it is probably the wrong code for that activity.
    Try grouping differently.
    Cheers.
  2. 0
    K D ·
    Hi.
    This feature is available in P6. so you should upgrade to P6.

    Regards
  3. 0
    Jiso Thomas ·
    Can you try to switch off reorganize Automatically in User preference under application caption.It may work for you.

    Regards,

    Jiso