Hi all.

When i copy a project within the same EPS in P6, the new project turns up with all filters empty (they are there with the filter names, but conditions are empty). All filters I use are under the "user defined" tab.

 

Is this fixable?

Cheers

 

Haakon

 

5 replies

Oldest first
  1. 0
    John Sims ·

    why not just apply the

    why not just apply the filters again?

  2. 0
    Håkon Haukebøe ·

    When i open the new project,

    When i open the new project, all filters are empty. That means I must re-define every parameter in them to make them work.

  3. 0
    John Sims ·

    so all the filters that you

    so all the filters that you have made in your user field are gone? is the same layout applied? if not make sure you have the same layout applied otherwise the filters will be different.

  4. 0
    Håkon Haukebøe ·

    All filters are there with

    All filters are there with the same name. They are empty, wich means the dont filter anything.

  5. 0
    Raymund de Laza ·

    You are using a filter

    You are using a filter criteria that is just applicable to the source project such as activitiy codes under project, etc...