Earned value report P5

Patrick HomerMember for 18 years 5 months
Created
4
1
0
I have created a earned value report in P5. I want the report to include just a few resources. In P3, I could select the resources on the Resource selection tab in report writer. How can I do this in P5?

4 replies

Oldest first
  1. 0
    K D ·
    Hi.
    When creating report you can define the filter for it.
    Where resource_ID = .... then.

    regards
  2. 0
    Patrick Homer ·
    It will not let me filter by resource id. That is the first thing I tried. It is not one of the options under the filters.
  3. 0
    K D ·
    Hi.
    I just checked. You can edit the report by "Wizard" and add a filter on resource. It work.
  4. 0
    Arnold Puy ·
    Hi Patrick,

    When creating Earned Value Report you can define the filter using:

    Where Resource IDs "Contains" Type the value of Resource ID. Instead of Resource Name.

    Thanks.


    Arnold