Suggestion need to use P6 for user from 4 offices

Duy HuynhMember for 18 years 5 months
Created
1
2
0
How about the following configuration,
we have 4 offices at different location A B C and D.
We will install everything at A and let user from B C and D access the project via internet(about 6 users).
The project will have about 70000 activities.
In our place there are only two WAN technologies: ADSL and Lease line.

Any suggestion in systems requirement and other configuration?
Thank you.

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Hi
    It depends on the spread of workload in the different offices.
    Basically there are three ways:
    - Citrix: No problem with big projects
    - Use the web component which is included in P6. May be someone has experience with this size of project together with web component.
    - If the others don’t work: Exchange Xer-files. Take care that the Admin preferences are the same in every side.

    First make a concept of the co-operation of the four sites.
    Good luck
    Dieter