How to Get the Late Curves for the Project

Amreshwar ShuklaMember for 23 years 5 months
Created
3
3
0
I have the cost loaded schedule and want to get cost loading across the project time line as per the late dates. What is the correct procedue to get these values in P6. Regards

3 replies

Oldest first
  1. 0
    Amreshwar Shukla ·
    Hai Friends,

    There are lot of posting on this issue but none of them are helpfull to me. In my programme cost is loaded as Expences so I can use the Resource profile as suggested by Mr.Paul earlier.

    The search function of PP are not working so it is not possible to digg old posting on this topic.

    ANY HELP FROM ANY CORNER??

    Thanks in advance.

    A.S.Shukla
  2. 0
    Amreshwar Shukla ·
    Hai Friends,

    There are lot of posting on this issue but none of them are helpfull to me. In my programme cost is loaded as Expences so I can not use the Resource profile as suggested by Mr.Paul earlier.

    The search function of PP are not working so it is not possible to digg old posting on this topic.

    ANY HELP FROM ANY CORNER??

    Thanks in advance.

    A.S.Shukla
  3. 0
    Shiv Rao ·
    Shukla ,

    You have to used the Time Distributed REport generation .

    From where you have to use selection of Time interval fields .

    You have to use :
    In the Cummulative Units : Drop down list .

    Select Cumm Remaining Late Units
    and Cumm Remaining Early Units

    Hope your surve shall be generated.

    Shiv