P6 Import from P3 Resource Problem
In the Open Standard
Riyadh YahiaMember for 18 years 2 months
- Created
- 3
- 2
0
I have Imported a Project in P3 to P6, the Problem I am Facing that, In P3 I defined labor and skilled labor as resources, after Converting to P6, I Noticed that the Labor Converted to Labor BUT the skiled labor become Non Labor. So the Budgeted labor unit in P3 is NOT Equal to the Budgeted labor Unit In P6.
My Queation is, is there any way to change the resource type in P6 from non labor to labor resource. Or How To Import from P3 without Passing through the same Problem ???
best regards
My Queation is, is there any way to change the resource type in P6 from non labor to labor resource. Or How To Import from P3 without Passing through the same Problem ???
best regards