Good Old EV again
In the Open Standard
Nigel WinkleyMember for 20 years 5 months
- Created
- 3
- 2
0
Morning All
Starting to use EV in anger and whilst sorting out budgets, forecast etc have started to use Store Period Performance.
If we then produce a report showing the period costs, we are getting actuals in the next future period plus a remaining. Historic is correct to the penny.
I have checked just about everything I can check - start, early start, planned start, actual start and finishes, budget, forecast, remaining, actual, remaining, original, at completion durations, etc., etc., etc. All are correct.
Anyone have any ideas as to why P3e (version 5, SP5) would be allocating future actuals beyond the data date (set to the minute by the way) some of which are negative!???
In confusion and frustration
Nige
Starting to use EV in anger and whilst sorting out budgets, forecast etc have started to use Store Period Performance.
If we then produce a report showing the period costs, we are getting actuals in the next future period plus a remaining. Historic is correct to the penny.
I have checked just about everything I can check - start, early start, planned start, actual start and finishes, budget, forecast, remaining, actual, remaining, original, at completion durations, etc., etc., etc. All are correct.
Anyone have any ideas as to why P3e (version 5, SP5) would be allocating future actuals beyond the data date (set to the minute by the way) some of which are negative!???
In confusion and frustration
Nige
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?