Skip to content

S Curves in P6 - how?

Christopher NicolasMember for 20 years 4 months
Created
332
23
0

A silly question I know but I can’t figure out how to produce an S Curve in P6 - I know how to in P3 but can’t figure it out in P6 - help please.......

332 replies

Oldest first
  1. 0
    Streetboy Streetboy ·
    tanx
  2. 0
    Nasreen Almutawa ·
    can i please get a copy as well at : almutan@equate.com
    Thank you
  3. 0
    Arnold Puy ·

    Already sent.

  4. 0
    Amreshwar Shukla ·
    Hi
    Could you pls send me how to make SCurve in P6 ..
    to shukla456@gmail.com

    Tx
    Shukla
  5. 0
    Ashwani Singhal ·
    Hi
    Could you pls send me how to make SCurve in P6 ..
    to ashwani1969@gmail.com

    Tx
    Ashwani
  6. 0
    Arnold Puy ·

    Already sent.
  7. 0
    Arvind Ramaganapathy ·
    Hi, Can you please send me a copy of the mentioned file at rv_989@yahoo.com. Thanks
  8. 0
    Erwin Gonzales ·
    Hi Arnold,

    Could you pls also send me the file on how to make SCurve in P6 ..
    here’s my account ---- erwingonzales.vyg24@yahoo.com.ph

    Thanks.
  9. 0
    Aravinth Kumar ·
    Hi Arnold,

    Can i have a copy of it, Thanks in advance.

    send it to varavinthkumar@gmail.com
  10. 0
    Arnold Puy ·

    Already sent.
  11. 0
    George Ridulme ·
    Hi Arnold,

    can you also send me a copy.

    my email add: grridulme@yahoo.com


    again, many thanks

    George
  12. 0
    Arnold Puy ·
    Hi George,

    Already sent.

  13. 0
    Shandiz Afshar ·
    Dear friends,

    I am pretty new here. I would like to mention an easy way to generate S-curve using Primavera data into excel.

    As you may know Primavera is not able to produce S-curves which include Late unites as well as early.

    Step 1: your schedule must be resourced.
    Step 2: you should maintain a base line to your Project (menu/Project/assign baseline) and then assign the maintained baseline to project
    Step 3: you should store a copy of your project (with no actual) it can be either project baseline or a copy of project.
    Step 4: you should create a new report using report wizard to get data from primavera. (menu/Tools/report wizard/new report)
    Step 5: tick time distributed data, select activity resource and role assignment – next : on column select role or resource, on group and sort tick grand totals and summaries and group by labour types – next :select your desire time scale, on fields select Cum early unites as well as late ones and actuals (Actuals must be 0) – next: run report select ASC|| file and a saving path.
    Step 6: now you have an excel spread sheet with early, late, actual unites and a time scale
    Step 7: by excel curve wizard your able to create banana s-curve, if you put actual values in the actual cells for each period you can measure actual project against late and early unites, if project runs between late and early it is doing well otherwise project will be on risk.

    I hope mentioned are useful. Good luck.
    Shandiz

  14. 0
    Arnold Puy ·
    Hi John,

    Already sent.

  15. 0
    Aikaz Zakia ·
    Hello Every body
    Thanks Shandiz for information that you gave, i am a young planner and i am starting with the S-curves

    for the S curve you talk about actual, early and late, each one of the earlier and the late represent the budgeted? this curves inform us about the Ressources but not about the project performence, is it true?.
    Also P6 represent earned value, budgeted and estiamted at completion, can we use this curves

    for evey body who have information please answer
  16. 0
    Bobby Cunningham ·
    Hi everyone,

    Could someone also send me a copy.

    Send to rcunningham@hess.com

    Many thanks
  17. 0
    Praju Satish ·
    Even I would like to have a copy of the same .Could pls somebody mail the same to prajus@gmail.com
  18. 0
    Arnold Puy ·

    Already sent.

  19. 0
    Shah Maqbool Alam ·
    Hi Arnold...
    I’m curious to know as to what have sent to fellow members, since evrbdy seems to be aking for that..
    Kindly share it with me as well, since I also generate S Curve, but in a bit different way...Top down estimation method...which is a bit simpler one...

    Plz do send it to me.

    Thanx.
  20. 0
    Arnold Puy ·
    Hi Shah,

    Send me your email address.

    Regards.

  21. 0
    Shah Maqbool Alam ·
    ya..
    I just forgot to do so...
    mailmaqbool@gmail.com
  22. 0
    Arnold Puy ·

    Already sent.

  23. 0
    Shah Maqbool Alam ·
    Hi Arnold,

    I’m not able to access/ retrieve it..
    Can u help me??
  24. 0
    Aravinth Kumar ·
    hi Arnold,

    can u also send the details.

    my id is varavinthkumar@gmail.com
  25. 0
    Arnold Puy ·
    Guys,

    Please follow this link and you can download it there:

    http://www.4shared.com/account/dir/14174063/81de5ac2/sharing.html?rnd=6

    Thanks.

    Arnold
  26. 0
    Shandiz Afshar ·
    The s-curves that I have mentioned are measuring project performance (timing), against baseline early and late dates.

    You could use Primavera EV s curves but in P6 you are able to have only early Curve against EV, but by the way that I have mentioned you are able check the Project performance (EV) against Late and Early units. If your EV (Actual) s-curve is moving inside the late and early area project is doing well if it is moving to above early curve project is performing perfect but if it is moving to late s-curve project is performing bad and if it is below the late s-curve project will be finished later than planned date. In this case, you as a planner should warn project manager for further action to be taken.

    In my opinion the other advantage of this s-curves is that as you generate them in excel you can report them more cosmetic and they look better than Primavera’s one.

    Cheers,
    Shandiz
  27. 0
    Saiful Adli Mohamad ·
    Arnold,

    i cant download the file from the link. could u please send it to my email? thanks in advance.

    regards,
    Saiful
    saiful@knpe.com.my
  28. 0
    Jose Ramirez ·
    Hey, Thanks the link works...
  29. 0
    Sabri Ghani ·
    hi arnold,

    i couldn’t download from your link, can you send to my email instead? thanks....

    sabrighanisan@gmail.com
  30. 0
    Arnold Puy ·
    Hi Sabri,

    Already sent.

  31. 0
    Simon Davies ·
    Please can I have a copy sent to Simon.Davies@kbr.com

    Many thanks, this is a hot topic for all.
  32. 0
    mariya Mariya ·
    Hi Arnold!
    Can I have a copy also?
    Looks like everyone found it useful.
    mailto:mariabondareva@mail.ru
  33. 0
    Arnold Puy ·
    Guys,

    Already sent.

  34. 0
    JV Amande ·

    hi Arnold,

    can you also give me copy about Early and Late S-curve application?

    what is my source data? is it the manpower? am confused?

    thanks..

    jV

    here is my e-mail address: jv_amande@yahoo.com
  35. 0
    D Artagnan ·
    guys, i just wanna share that i was able to make an excel sheet that automatically generates s-curve and cash flow, it’s fully editable using the feature of pivot reporting. if interested just send me an email. The data, btw, are parsed thru ms access.
  36. 0
    Arnold Puy ·
    Hi JV,

    Already sent.

  37. 0
    Shaun Draper ·
    hi, could i also be sent a copy, will find it very useful.

    s.draper@globalplanningservices.com.au
  38. 0
    Sam Choy Ha ·
    hi, can u send me a copy as well?
    my email is samc0002@ntu.edu.sg

    Thanks!!
  39. 0
    Athar Hashmi ·
    Hi Arnold,
    Please send me too, s-curve generation program.
    athar.hashmi@yahoo.com

    Thanx
  40. 0
    Arnold Puy ·

    Already sent.

  41. 0
    JV Amande ·


    Arnold,

    Thanks for the manual. Surely it will help my planning work a lot.

    Just additional Question.

    regarding my resources histogram.

    im just confused with the output.

    ex. week-1 (equipment histogram)

    the output of average... = to the minimum qty. used
    the output of peak = to the maximum qty. used
    the total = it sum-up the qty used from
    (Day1-Day6)

    now, i want to ask which one is the best reference for reporting purposes.

    in addition to this, i’m also confused with my reporting, specifically in excel where i tabulate requipment & labor from week-1 up to the last week.

    In normal week sequence,
    ex. week-1 (Sat.Sun.Mon.Tue.Weds.thurs.)

    but my schedule start at Weds., therefore my week-1 only have 2-days (weds.thurs.) and here i already start allocating my resources (Labor& eqpmt)

    my question is that, why is it on the LAST-WEEK, i have no more inputs. is this only normal? i think its because of the two days where i start my Week-1.

    thank you and hope to hear your response soon.

    Sir, can you please send me a P3 manual.


    Thanks and More Power.




  42. 0
    Athar Hashmi ·
    Thanx Arnold,
    You have done a great job. It’s very nice.
    May Allah bless you here and here after!
  43. 0
    Arnold Puy ·
    Hi Athar,

    You are welcome.

    Alhamdulillah!

  44. 0
    Joseph Erwin Cargason, C.E.,PSP ·
    Dear Arnold,

    Good day, can i also have a copy of this steps on how to generate an s curve with p6?

    my email address is jcargason@yahoo.com

    thank you and Best regards,


    Joseph
  45. 0
    Didith D. ·
    Hi Arnold, that will be very useful in planning, can I also have the manual? please send it to shirley.dichoso@yahoo.com. Thanks so much....
  46. 0
    Sakandar Hayaat ·
    Hi Arnold,
    Its nice that you are helping people in understanding and proper utilization of P6.
    Can I also request you to send me manual and how to create histogram in P6.

    Regards,

    Sikandar
  47. 0
    Hadi Mahmoodvand ·
    Hi Arnold

    can you also send me a copy.

    my email address: mahmoodvand@gmail.com

    again, many thanks

    Hadi
  48. 0
    Ashutosh Nema, PMP ·
    Dear Arnold,
    Please send me the same.

    My Email Id is
    ashutoshnema19@gmail.com

    Best Regards,
    Ashutosh Nema
  49. 0
    Albert Valencia ·
    Hi Arnold,

    Can you send me the instruction as well? abv16@yahoo.com

    Thanks!

    -Albert
  50. 0
    Jannell Boland ·
    Hi Arnold,

    could you please forward me the information on resources and s curves? it would be REALLY helpful!

    jannell_b@hotmail.com

    Regards

    Jannell

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?