Using contractor P3.1 subprojects with P6

Deborah JoyMember for 18 years 4 months
Created
2
3
0
We are upgrading from P3.1 to P6. We have schedules with sub-projects that are updated remotely by the contractors and data is exchanged via PRD files. Once schedules are migrated to P6, will we still have this functionality? (Sorry if this has already been addressed, but the "search" function within forum threads isn’t working and I’ve spent as much time as I can on searching through all the previous posts...)

Deb

2 replies

Oldest first
  1. 0
    David Forrest ·
    Unfortunately PRMail does not exist in P6, suggest you use check-out and check in feature, you can also check what has changed by using claim digger.


    Other option is to use P6 Web.

    Regards
  2. 0
    Deborah Joy ·
    Thank you, David. I won’t have training until next week, but am working my way through a P6 book so will watch for more information on these features.

    Deb