Thanks for reply, I have set up a project calender which works 24 hours 7 days a week, however the default calender in the enterprise-calendar-global is only on a 37.5hour week. I have tried to change it but it wont let me. Do you know how i get around this as at the moment my summary bars are of no use.

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Dave
    I assume you related this question to your thread on summary bars.
    You may use level of efforts with the calendar you need.
    Default calendar ist for the whole database, i.e. for all users and all projects. To change is assigned to certain user privileges.
    Dieter