Task ordering against WBS

Jim SandersMember for 18 years
Created
3
3
0
Hi all,

Am I right in thinking that regardless of the sort order selected, within a WBS level the first items to be shown will be the activities at that level then followed by any lower level WBSs?

e.g.

WBS L2
Activity 1
Activity 2
WBS L3
WBS L3
WBS L2
etc.

Is there any way of having the activities appear after the lower level WBSs?
like
WBS L2
WBS L3
WBS L3
Activity 1
Activity 2
WBS L2

I know that I can create additional WBS L3 to hold the activities, but if I wanted a milestone under L2, summarising the dates from L3 then it appear first when I’d really like it to be afterwards.

Cheers
Jim

3 replies

Oldest first
  1. 0
    Steven Oliver ·
    You can change the order that wbs bands are displayed, if that is what you are after.
  2. 0
    Jim Sanders ·
    Hi Steven,

    Thanks for replying.

    Unfortunately I’m after a way of changing the order of where the activities are in relationship to the sub-WBSs.

    To clarify - If I have a series of WBS groups of activities and I then want a milestone driven by the latest activity of them then I would like the milestone to be listed after the WBS groups (as I logically like my plans to waterfall down - the latter activities appearing lower in the list than the earliest). It’s currently showing the milestone before the WBSs.

    Cheers
    Jim
  3. 0
    Steven Oliver ·
    I think, that I would go with a combination of WBS (to level 1) and activity codes.