Show P3 trace logic in bar chart

Anu TorMember for 19 years 7 months
Created
2
3
0
Good afternoon,

I want to trace the driving logic of predecessor and successor in bar chart same as pert chart.

Anyone can recommend me the method to do in P3 or other software to support one.

Thanks,

2 replies

Oldest first
  1. 0
    Ali Farhat ·
    Anu,
    I didnt get your question perfectly...anyhow, driving relationships are displayed in Gantt and pert chart as solid lines while nondriving relationships are displayed dotted line.
    Is that what you want?
  2. 0
    Anu Tor ·
    Hello Ali Farhat,

    In normally, P3 will show all links if select one. In sometime, If I select a activity and want to see 3 level of predecessors and successors of one in bar chart format.

    Please recommend me.