Recurrent Tasks

Ali FarhatMember for 17 years 11 months
Created
4
3
0
A simple question,
How can I create a recurrent tasks in P6?
I tried the following but each has its own restrictions
1- Defined a special calendar for the task, and gave the task the duration of the whole project
restriction: the task only appears once when I group my activities per "Start Date" and I want it to appear in each time interval

2- Create more than one activity, link them with a lag, schedule using 24hr calendar lag
restriction: if one activity gets delayed, it will affect its successor..and this is not the real case. not to mention it is time consuming

Is there other way round?

4 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Ali
    Recurrent tasks do not exist in Primavera.
    For my experience those are tasks such as meetings, reports etc. which are important but no need to trace if they were on time.
    In general I use the type level of effort and assign the resources with an appropriate rate, e.g. 2 hours a week.
    If you must trace if they were done one time you’ll need an activity per period.
    Sorry, no ideal solution.
    Regards and a happy new year!
    Dieter
  2. 0
    Ali Farhat ·
    Isnt there a way to ask primavera company or Oracle to add this feature? It can be added to activity types.
  3. 0
    Dieter Wambach ·
    You can ask Primavera, of course. Via your Primavera vendor or directly. It is a customer-driven product.
  4. 0
    Alexandre Faulx-Briole ·
    Hello all,
    P3 has an Excel utility to insert recurring task; P3e, PM4/5/6 has not
    Alexandre

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?